December 7, 2022 – PennDOT District 6 Executive Lou Belmonte was joined by local and elected officials in Bensalem Township, Bucks County today to celebrate the completion of the U.S. 1 Section RC1 improvement project and to highlight the departments’ 2022 construction season that included 55 new contracts worth an estimated $800 million to repair, reconstruct and improve state highways and bridges across Bucks, Chester, Delaware, Montgomery and Philadelphia counties.
“It’s a significant achievement to deliver these types of large investments to improve our roadways and bridges,” said District 6 Executive Louis Belmonte. “From large scale corridor-wide programs and intersection improvement projects to roadway resurfacing and repairing bridges, we’re laser-focused on enhancing the safety and efficiency of our transportation network.”
PennDOT District 6 currently has more than 135 projects currently under construction valued at more than $2 billion. Several of the projects are supported and accelerated by the federal Bipartisan Infrastructure Law (BIL). In 2022 alone, the BIL is bringing at least $115 million in additional funding to the District 6 region to be allocated by the department and the Delaware Valley Regional Planning Commission.
Some of the most notable construction projects that began this year include:
Some of the most notable projects that were completed this year include:
The news conference today also celebrated the completion of PennDOT’s $94.5 million U.S. 1 Section RC1 project to widen and reconstruct more than a mile of U.S. 1 between Old Lincoln Highway and the Pennsylvania Turnpike and improve the U.S. 1 interchanges at the Turnpike and at Street Road (Route 132).
Section RC1 also included replacement of U.S. 1 bridges over Street Road (Route 132), the Pennsylvania Turnpike, and the Turnpike’s interchange ramps with wider structures to accommodate additional lanes on U.S. 1. The new bridges have improved vertical clearance for the increased height of today’s commercial vehicles. The Bristol Road bridge over U.S. 1 also was replaced with a longer span to provide room for widening U.S. 1 that is currently underway as part of the adjacent Section RC2 project.
Additionally, under the Section RC 1 contract, the old guide rail median on U.S. 1 was replaced with a new concrete median/glare screen, a northbound lane was added at the intersection of U.S. 1 and Old Lincoln Highway, a new stormwater drainage system was installed, and sound walls were added along southbound U.S. 1 south of the Turnpike.
The project also included major improvements to the U.S. 1/Street Road (Route 132) Interchange. The original ramps to and from U.S. 1 north were replaced with new ramps at a signalized intersection on the south side of the interchange. The ramps from U.S. 1 South to eastbound and westbound Street Road (Route 132) and from westbound Street Road (Route 132) also were replaced at a new signalized intersection. And a new ramp to southbound U.S. 1 from eastbound Street Road (Route 132) also was constructed.
Ramps to and from U.S. 1 and the Turnpike interchange were reconstructed with improved turning geometry to meet current design standards. A second lane was added to the ramp from northbound U.S. 1 to the Turnpike and from southbound U.S. 1 to the Turnpike.
Section RC1 is the first of three construction contracts that comprise PennDOT’s U.S. 1 Improvement Project to widen U.S. 1 (Lincoln Highway), replace aging bridges, and complete a number of highway safety enhancements along a five-mile segment of U.S. 1 that extends from Old Lincoln Highway to just north of the Corn Crib Lane overpass in Bensalem and Middletown townships and Langhorne Manor and Langhorne boroughs.
Construction is currently underway on Section RC2 to the north, where U.S. 1 is being widened and new bridges are under construction over the Neshaminy Creek, over ramps and rail lines at the Penndel/Business U.S. 1 Interchange, and over Rockhill Drive at the Neshaminy Interchange.
A third project, Section RC3, will improve U.S. 1 from north of the Penndel/Business U.S. 1 Interchange to north of the Corn Crib Lane overpass in Middletown Township and Langhorne Manor and Langhorne boroughs. Section RC3 is currently progressing through the preliminary engineering stage and is anticipated to move into final design in early 2024. The project is advancing toward construction beginning in late 2026.
For more information on additional improvement under the Section RC1 contract and PennDOT’s entire U.S. 1 reconstruction program in Bucks County, visit www.us1bucks.com.
Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.