322 Conchester Highway

Conchester Highway

Project Information

Section 103*

Construction Start: 2024
Construction Completion: TBD
Cost: Est. $90 million
General Contractor: TBD

*Section 103 remains in Design. Details of improvements shown at this time are subject to change.

Roadway Improvements

Reconstruct the existing four lane, barrier-separated section of U.S. 322 (Conchester Highway) from Cherry Tree Road/Bethel Avenue to just east of Route 452 (Market Street).

Intersection/Interchange Improvements

(Click individual intersection for more details.)

Cherry Tree Road/Bethel Avenue

  • Reconfigure and reconstruct the intersection with U.S. 322 (Conchester Highway)
  • Install new traffic signal
  • Install left turn lanes at the intersection
  • Realign Bethel Avenue/Cherry Tree Road intersection to Hilltop Elementary driveway

Route 452 (Market Street) Interchange

  • Reconfigure and reconstruct the U.S. 322 (Conchester Highway) Interchange
  • Add two new traffic signals
  • Reconstruct Bethel Avenue from Dutton Street to Route 452 (Market Street)

Section 103*

*Section 103 remains in Design. Details of improvements shown at this time are subject to change.

Existing two lane section

Existing four-lane section, barrier separated, no shoulders

New four-lane section with curbed grass median

New four-lane section, barrier separated with shoulders

New four lane section with left turn lane