Construction Start: 2024
Construction Completion: TBD
Cost: Est. $90 million
General Contractor: TBD
*Section 103 remains in Design. Details of improvements shown at this time are subject to change.
Reconstruct the existing four lane, barrier-separated section of U.S. 322 (Conchester Highway) from Cherry Tree Road/Bethel Avenue to just east of Route 452 (Market Street).
(Click individual intersection for more details.)
Existing two lane section
Existing four-lane section, barrier separated, no shoulders
New four-lane section with curbed grass median
New four-lane section, barrier separated with shoulders
New four lane section with left turn lane