Section 103


Construction Start: Late 2024
Construction Completion: 2030
Cost: $99.5 million
General Contractor: R.E. Pierson Construction Co. Inc., of Pilesgrove NJ.


ROADWAY IMPROVEMENTS

Section 103 will improve U.S. 322 (Conchester Highway) from just east of Chelsea Parkway/Bethel Avenue to just east of Route 452 (Market Street), reconstructing and widening the two-lane section and its intersections to four travel lanes with turn lanes, and reconstructing the four-lane section and widening the shoulders and median.


INTERSECTION/INTERCHANGE IMPROVEMENTS

(Click individual intersection for more details.)

Cherry Tree Road/Bethel Avenue

  • Reconfigure and reconstruct the intersection with U.S. 322 (Conchester Highway)
  • Install a new traffic signal
  • Install left turn lanes at the intersection
  • Realign Bethel Avenue/Cherry Tree Road intersection to Hilltop Elementary driveway

Route 452 (Market Street) Interchange

  • Reconfigure and reconstruct the U.S. 322 (Conchester Highway) Interchange
  • Add two new traffic signals
  • Reconstruct Bethel Avenue from Dutton Street to Route 452 (Market Street)