Bridge Construction, Eastbound Widening, Drainage, Utility Construction Continuing This Fall on U.S. 322 (Conchester Highway) in Delaware County
Activities to reconstruct and widen the eastbound side of U.S. 322 (Conchester Highway) between Chelsea Parkway/Bethel Avenue and the Market Street Interchange (Section 103) are progressing this fall.
Underground utility relocations along Route 452 (Market Street) are ongoing and will continue through the fall. Overhead utility relocations are mostly complete project-wide.
Crews will continue to construct the first section of the new U.S. 322 bridge over Route 452 (Market Street). The bridge deck was placed on October 5, 2026. This section will carry U.S. 322 eastbound traffic in its final configuration. The westbound side of the bridge will be constructed in a later stage.
Crews also continued retaining wall and sound barrier wall construction (see photos above) along eastbound U.S. 322.
Roadway construction to widen U.S. 322 eastbound continued. Work includes new curb, drainage, and new signal poles. Asphalt paving along Bethel Ave and U.S. 322 at the intersection of Cherry Tree Road was completed in mid-October.
Oliver Lane at Kates Glen remains closed for the construction of new cul-de-sacs. There will no longer be access from Kates Glen to Flora Lane via Oliver Lane.
U.S. 322 remains one lane in each direction through the work area, with traffic shifted onto the north (westbound) side to allow for construction on the south (eastbound) side. PennDOT will continue to maintain at least one lane of traffic in each direction except during occasional, flagger-controlled restrictions at various times and locations. Access will be maintained as well to all residences and businesses within the work area during construction.
The $99.4 million Section 103 project will reconstruct and widen the highway to four travel lanes from just east of Chelsea Parkway/Bethel Avenue to the existing four-lane section approaching Route 452 (Market Street); improve the Cherry Tree Road/Bethel Avenue intersection; and reconfigure the U.S. 322/Route 452 interchange, including replacement of the bridge over Route 452 (see below).
The Section 103 project is the second of four construction contracts under PennDOT’s U.S. 322 (Conchester Highway) Improvement Program to improve travel and safety on a 6.7-mile section of U.S. 322 in Concord, Bethel, and Upper Chichester townships.
R.E. Pierson Construction Co. Inc., of Pilesgrove, N.J., is the general contractor on Section 103. The project is financed with 80 percent federal funds and 20 percent state funds.
Section CSX, a $63.4 million infrastructure investment to replace the bridge over the railroad and improve the Bethel Road/Highland Road interchange, is currently under construction immediately east of Section 103.
Section 101 widening and intersection improvements were completed in 2020 between U.S. 1 (Baltimore Pike) and Clayton Park Drive.
Final engineering design is advancing for Section 102, the widening and reconstruction from Clayton Park Drive to Chelsea Parkway/Bethel Avenue. Section 102, which is not yet scheduled for construction, will wrap up PennDOT’s improvements to U.S. 322 between U.S. 1 (Baltimore Pike) and I-95.
Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/