Section CSX Construction Update: Fall 2026

Traffic Shifts, Bridge Foundation Construction This Fall 

Following almost six months of mostly utility installations and relocations, construction activity on the U.S. 322 CSX project will increase this fall with implementation of an expanded traffic pattern on U.S. 322 (Conchester Highway) and foundation work for the U.S. 322 bridge over the CSX railroad.

Water, gas, and fiber optic utility work continues across the project area through the remainder of the year. Drainage work is expected to begin in November along Bethel Avenue and eastbound U.S. 322.

Construction crews shifted traffic and placed long-term construction barriers on U.S. 322 east of the CSX bridge in mid-October (see above). Crews will then install temporary support of excavation in preparation for subsequent construction of abutments for the new bridge for the remainder of 2026. The shift will move westbound traffic to a single lane to the north and a single lane of eastbound traffic to the south.

With traffic shifted to the outside eastbound and westbound lanes, construction crews will remove the existing median barrier to prepare for a later traffic shift in early 2027. That shift will move eastbound and westbound vehicles to one side of the highway into a long-term traffic pattern for the demolition and reconstruction of half of the new CSX Bridge.

The contractor will also begin work on a culvert under U.S. 322 at the western end of the work zone this fall.

Work at the intersection of Highland and Bethel avenues will also continue this fall. Intersection work includes new curbs, ADA ramps, and traffic signal poles. Drivers may experience periodic off-peak daytime lane closures during this time.

Section CSX, a $63.4 million infrastructure investment, will replace the bridge over the railroad (see below) and improve the Bethel Road/Highland Road interchange.

Work on the CSX project is being coordinated with Section 103 improvements currently under construction to the west.

The Section CSX project is the third of four construction contracts under PennDOT’s U.S. 322 (Conchester Highway) Improvement Program to improve travel and safety on a 6.7-mile section of U.S. 322 in Concord, Bethel, and Upper Chichester townships.

JD Eckman Construction Inc. of Atglen, PA, is the general contractor for Section CSX. The project is financed with 80 percent federal funds and 20 percent state funds.

Section 101 widening and intersection improvements were completed in 2020 between U.S. 1 (Baltimore Pike) and Clayton Park Drive.

Final engineering design is advancing for Section 102, the widening and reconstruction from Clayton Park Drive to Chelsea Parkway/Bethel Avenue. Section 102 construction, which is not yet scheduled for construction, will wrap up PennDOT’s improvements to U.S. 322 between U.S. 1 (Baltimore Pike) and I-95.

Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT’s planned and active construction projects at www.projects.penndot.gov.